Barber Street Improvements


UPDATE OF BARBER STREET RECONSTRUCTION - AUGUST 23, 2010

PHASE 2 OF THE BARBER STREET PROJECT, (BETWEEN TULIP AND ROLLING HILL), WILL BE CLOSED TO ALL THROUGH TRAFFIC, STARTING MONDAY, AUGUST 30, 2010 TO OCTOBER 31, 2010, WEATHER PERMITTING. THE ONLY TRAFFIC PERMITTED IN THIS AREA WILL BE THE RESIDENTS THAT RESIDE IN THIS SECTION. TO ACCESS YOUR HOME YOU MAY NEED TO FOLLOW THE DETOUR ROUTE AND COME IN OFF OF A SIDESTREET. THE SAME ACCESS WILL BE AVAILABLE FOR ANY SERVICES, GARBAGE, AND MAIL DELIVERY.

IN ADDITION IF YOU HAVE ANY IRRIGATION IN THE CITY OF SEBASTIAN RIGHT OF WAY IT WILL NEED TO BE REMOVED FROM THE RIGHT OF WAY. ANY IRRIGATION THAT THE CONTRACTOR ENCOUNTERS DURING CONSTRUCTION WILL BE CUT AND CAPPED OFF AT THE RIGHT OF WAY. REINSTALLATION OF THE IRRIGATION WILL BE THE HOMEOWNERS RESPONSIBILITY.

PLEASE FOLLOW THE POSTED DETOUR SIGNS, AND AS ALWAYS, PLEASE HELP KEEP THE WORK AREA SAFE BY OBSERVING SPEED LIMITS AND OTHER POSTED SIGNS.

FOR QUESTIONS PLEASE CONTACT GINNY SIEFERD AT THE CITY OF SEBASTIAN
(772)-388-8222

 
20100813 - Barber Street Paving Project update

BARBER STREET, PHASE 4 OF THE PROJECT, WILL REMAIN CLOSED BETWEEN FILBERT ST. AND FRIAR CT., THOUGH MONDAY, AUGUST 16, 2010.  PLEASE FOLLOW THE POSTED DETOUR SIGNS, AND AS ALWAYS, PLEASE HELP KEEP THE WORK AREA SAFE BY OBSERVING SPEED LIMITS AND OTHER POSTED SIGNS.

 
20100809 - Barber Street Paving Project Update

BARBER STREET, PHASE 4 OF THE PROJECT, WILL REMAIN CLOSED BETWEEN FILBERT ST. AND FRIAR CT., UNTILL AUGUST 12, 2010. PLEASE FOLLOW THE POSTED DETOUR SIGNS, AND AS ALWAYS,
PLEASE HELP KEEP THE WORK AREA SAFE BY OBSERVING SPEED LIMITS AND OTHER POSTED SIGNS.

 
UPDATE OF BARBER STREET PAVING PROJECT July 29, 2010

BARBER STREET, PHASE 4 OF THE PROJECT, WILL REMAINED CLOSED BETWEEN FILBERT ST. AND FRIAR CT., UNTILL AUGUST 10, 2010. PLEASE FOLLOW THE POSTED DETOUR SIGNS, AND AS ALWAYS,

PLEASE HELP KEEP THE WORK AREA SAFE BY OBSERVING SPEED LIMITS AND OTHER POSTED SIGNS.

 
Update Of Barber Street Paving Project

Starting The Week Of July 12, 2010 Work Will Begin On Phase 4 Of The Project. This A Week Later Then First Stated, Sorry For Any Inconvenience.
Phase 4 Is Between Addie And Shumann. There Will Be Lane Closers, And Detours.
Please Help Keep The Work Area Safe By Observing Speed Limits And Other Posted Signs.

 
20100623 - Barber Street Update

UPDATE OF BARBER STREET PAVING PROJECT

STARTING THE WEEK OF JULY 5, 2010 WORK WILL BEGIN ON PHASE 4 OF THE PROJECT. PHASE 4 IS BETWEEN ADDIE AND SHUMANN. THERE WILL BE LANE CLOSERS, AND DETOURS.

PLEASE HELP KEEP THE WORK AREA SAFE BY OBSERVING SPEED LIMITS AND OTHER POSTED SIGNS.

 
BARBER STREET RENOVATION PROJECT - UPDATE

MAY 7, 2010

As FDOT manages the Barber Street Renovation Project, the City will be making every effort to keep citizens informed about construction progress. This posting marks the first update.

Shortly, the contractor will begin compacting the road. As a result, residents/Business along Barber St. may feel vibrations. These vibrations should not damage private property.

Keep watching for more updates as we move forward with this project. And, as always, please obey the detour signs. Use only the closed section of Barber St. if you live or have business in the construction zone. For other information, please contact Ginny Sieferd at (772) 388-8222

 
Phase 1 Detour Information

Beginning April 12, 2010 you will begin to see activity along Barber Street in Phase I
Please be aware of this activity, use caution and follow detour signs as outlined below.

BarberSt_ph1

Any question, please contact Ginny Sieferd at 772-388-8222 or e-mail This e-mail address is being protected from spambots. You need JavaScript enabled to view it

 
Barber Street Improvements Delay

I have been informed by the FDOT that the scheduled start day for the Barber Street renovation project will be delayed from February 11 for 45 days. FDOT is hopeful that the full 45 days will not be required and, in the end, the project final completion date will not be significantly altered.

The reason for the delay is in SJRWMD permitting. At the design portion of the project FDOT was under an assumption that the milling and raising of Barber Street was an exemption to stormwater permitting under the ARRA (American Reinvestment and Recovery Act). However, it has been recently determined that this assumption was in error. After quickly consulting with SJRWMD officials, FDOT representatives have filed the correct permits and will be using every effort to seek an immediate approval of permits. Both SJRWMD and FDOT representatives do not believe the review will modify design; the delay is considered administrative only.

 
Barber Street Improvements - Pg1

BarberPg1

PDF of Above Information

 